| Project Name | When initiated | Date finished | Details | extra info | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Main Gate | 2001 | current |
2017 The Main Gate was repainted in July.
2017 The motor driving the main gate was replaced in Dec 2017 for $7000. 2019: The key pad was replaced in Feb 2019. In 2019, the north wing of the gate was damaged in two independent car accidens. Unfortunatedly we were unable to identify the person responsible for the second accident and the subdivision had to pay for the repair. | Entry codes: 2580 and 1224. Toggle code 1414. | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| County Easement on the west side of CKE and parallel to Casey Key Road | 2001 | future | We are trying to relocate Kingsway further west through
the County easement alongside Casey Key Road. Joan is applying for a permit.
We will ask our Landscaper Absolute Lawn to do it.
No County permission yet | Work in progress | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Kingsway, between lot 12-14 and the Casey Key Road Easement | 2002 | Ongoing maintenance | Because some homeowners (lot 13) preferred renewal of shell stone cover we abandoned the original plan to resurface Kingsway with cement brick paving stone. We renewed the shell stone in 2019. It may need fortification towards the trench side to prevent the shell-stone migration into the ditch. 2020: there is a new request to erect the fence west of kingsway. We have bids. Shall we do it before the final loacation for kingsway is determined? Questions to be answered at the next meeting: Proceed with fence? Add border stones on the weste side? | DECIDE | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Landscaping | 2001 | ongoing | link 76 Landscaping | repair link | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Queensway
(An old deterioriated walkway on the south border of CKE).
| 2002
| The reconsruction plan is to hide Queensway visually from surrounding
building and connect our beach access to the tennis court area
|
Queensway is located on a 300 foot County Utility Easement on the southern edge
of CKE and west to the intracoastal canal. It has been secured with shellstones in 2004 (see map)
and extends through the south borders of lot 12 and 11 and possibly mangrove area.
| County permission is required because reconstruction of Queensway involves part of a CE and some swale-area of lot 12 and 11. Permitting should be done in connection with the seawall permitting . Questions to be answered at the next meeting: Proceed with fence? Obtain verbal approval[93]
| Fishing pier
| see plans
| ongoing
| The fishing pier is detoriating and needs repair at several spots. | Casey Milford got estimate to construct a Kayak launch platform. 1. Offer for about $ 800 2. Offer for about $2800 3. Offer for about $16,000 Questions to be answered at the next meeting: Decide which offfer Decide when to repair fishing pier DECIDE
| [127] Lot 7 Park
| 2004
| ongoing
| in good shape. Some trees need prunig and shell stone cover might be refilled.
| OK
| [129] Gulf Winds Way
| 1998
| after construction of lot 13 is completed
| There are many cracks in the concrete cover that need major work In the past two years we have consulted several specialists and got many opinions for reconstruction.
| It does not make sense to have two drainage swales parallel on
the south side of Gulf Winds Way. Decide if the concrete cover should be replaced with a more friendly
looking paver or a combination of both.
| [138]Tennis Court | 2017 | 2018 | Irma damaged the north fence. It was repaired in March 2018. | Gate to King's Way | 2017 | 2018 | A member suggested to have a gate located across the street from our current beach lot gate to provide more privacy. The gate would lead to Kings Way and be constructed similar to the beach lot gate. Bid for the work will be presented at the 2019 annual meeting. | Gazebo | 2002 | 2018 | Parts of the gazebo are rotten and need repair and a new paint job. The gazebo roof also needs repair. | Signs at the front entrance | 2018 | 2018 | need maintenance | Vacation of CE overlay of Unit 2 | 2017 | 2018 | Civil engineer Mark Gollnick, PE is working together with Dietmar on this rather complex project. There are 10 documents that were prepared. The final application has been submitted. County is very slow to react. Dietmars MVA delayed the progres of this project. | 030 Permits - Agreements - Contracts | nd | Permits will be listed here | [34] Beach Lot Access Rental | Our Beach | Current | 42 Mr. and Mrs. Parm did aquired the right to use our Beach Lot for $ 150,000.00 and an annual maintance fee. | All but one Homeowner agreed to the deal | Surface Water Management Permit | 1997 | 2017 | The stormwater drainage system has been inspected and certified in Dec 2017 by the engineer. Brian paid the fee of @ 275 and submitted the reort to the County. | Permit NO:44 474.002 valid till 2029 | Beach Lot | 2001 | Current | Our Beach Unfortunatedly the beautifull two-colered bourgainvilla was removed by previous gardners. There is now a non prospering Queen palm. We may want to plant some Coconut palms in free spaces | awaiting sugestion from members. |